An equipment asset register template for Excel needs about a dozen columns: a unique ID, category, manufacturer, model, serial number, rating, location, condition, warranty end date and a reference to the evidence. Most downloads stop at the headings. This guide gives the columns, where each value comes from on site, a worked example, and how to stop Excel turning serials into 1.2E+11.
The short answer: what the register is for and what goes wrong without it
Designing Buildings describes an asset register as an itemised list of a building’s components, with the extra information needed to inspect, maintain, clean and replace them. It often sits inside the owner’s operation and maintenance manual, and the facilities team uses it to plan inspections and repairs. Its typical entries include description, identification number, location, supplier and installer, condition and defects, photographs, certification and warranties.
Without it, the person who inherits the site has a pile of invoices and a roof they cannot easily climb. They cannot tell which inverter is which, which warranty clock started when, or which unit was damaged on delivery. A register written at the unit, by the people who fitted it, removes that guessing.
What the guidance actually asks for
Designing Buildings’ page on registers for construction projects says the end client and their advisers should define the content, and that the main contractor normally produces it as part of the agreed handover deliverables. It is built up in stages: intended assets, locations and IDs at design, then as-installed manufacturer, model or part number and warranty end dates during construction, then commissioning and tagging data before handover. Where the client is unclear, it points to the UK BIM Framework, based on COBie, as the industry standard for what to include.
Yale’s Office of Facilities shows what a client can ask for in practice. Its equipment nameplate data matrix has contractors enter as-installed nameplate data for each asset: an equipment number starting at 001, a description, an asset group picked from a list, building and room, manufacturer, part number, model number, serial number, acquisition date and warranty end date. The shape is a useful model for an installer: one row per unit, copied from the plate.
Public bodies set accounting minimums. The Scottish Public Finance Manual lists what the asset is, where it is, when it was acquired, what was paid, expected useful life, the cost centre and the source of funds. Those are finance fields. A handover register for installed equipment keeps some of them and adds the physical facts that only the site can supply.
Aconex, a construction platform, makes a related point about process: to build a handover manual, issue suppliers an Excel template that is empty except for column headers, one column for each kind of information you want about each asset. Agree the headings before the work starts, not after.
The columns, field by field
This is the column set we would use for installed solar, battery, heat pump, HVAC or switchgear equipment. The last column matters most for a crew: it says where the value comes from, so nobody types from memory.
| Column | What goes in it | Example | Where it comes from on site |
|---|---|---|---|
| Item | A unique number that ties the line to its evidence | 007 | Allocated once per unit and never reused |
| Category | The equipment type, so the register can be read by family | Inverter | Chosen by the crew when the unit is photographed |
| Manufacturer | Maker as printed on the plate | Sungrow | The nameplate |
| Model | Model or part number as printed | SG110CX | The nameplate |
| Serial number | Exactly as printed, stored as text | A2105001234 | The nameplate |
| Rating / capacity | The headline rating the plate states | 110 kW | The nameplate |
| Condition | New, or what is wrong, with a note | New | Judged at the unit by the crew |
| Location | Where the unit sits on the site | Plant room, bay 2 | Typed by the crew while standing there |
| Warranty end date | Start date plus length, as an end date | 11 Sep 2036 | The warranty paperwork, set per equipment type |
| Site tag | The client’s own identifier, if they use one | INV-01 | The client’s drawings or labels |
| Additional specifications | Other labelled details the plate states | IP66; 3 MPPT | The nameplate, line by line |
| Evidence reference | Where the nameplate photo can be found | Page 12 | Added when the pack is built |
A column checklist you can copy
Paste this into the first row of a new sheet, then delete what the client does not want. Keep the order: identity first, then what it is, then where it is, then its state, then its paperwork.
- Item (unique number, never reused)
- Category (equipment type)
- Manufacturer
- Model
- Serial number (format the column as Text before typing anything)
- Rating / capacity
- Location
- Condition (and a note if it is not new)
- Warranty end date (and the start date it was worked from)
- Site tag (the client’s own ID, if they have one)
- Additional specifications
- Evidence reference (photo page or file name)
A worked example: six rows
Here is how a small plant room might look. The values are invented for illustration. Notice that the serial on the third row has leading zeros and that the battery serial on the fourth is long enough to be damaged by a number format.
| Item | Category | Manufacturer | Model | Serial number | Condition | Location |
|---|---|---|---|---|---|---|
| 001 | Inverter | ExampleMaker | EM-110K | SN0012345 | New | Plant room, bay 1 |
| 002 | Inverter | ExampleMaker | EM-110K | SN0012346 | New | Plant room, bay 2 |
| 003 | Battery | SampleCell | SC-100 | 000123456789 | New | Battery store |
| 004 | Battery | SampleCell | SC-100 | 123456789012345678 | Damaged: dent on casing | Battery store |
| 005 | Switchgear | DemoGrid | DG-AC4 | 10-3 | New | Main LV room |
| 006 | Panel | SolarSample | SS-545M | PN2400056 | New | Roof, array A |
How to stop Excel mangling serial numbers
Microsoft’s support guidance says Excel removes leading zeros by default, converts large numbers to scientific notation such as 1.23E+15, and has a maximum precision of 15 significant digits, so anything past the 15th digit of a long number is turned into a zero. The Text format keeps entries as typed, but it only affects numbers entered after you apply it. A leading apostrophe also makes Excel treat an entry as text.
The Clean Energy Regulator, which collects inverter serial numbers in Australia, gives the same warning in its ledger guidance: a serial of 12 or more digits and no letters is converted to scientific notation automatically. It tells users to set the serial column to Text, not Number, and to open the exported CSV in Notepad to check what is really stored.
- Create the sheet and select the whole Serial number column before you type or paste anything.
- Set the column’s number format to Text.
- Type or paste the serials. A value that has already been converted cannot be rebuilt from the cell, so re-enter it from the source.
- If you import a CSV, use Data, From Text/CSV and set the serial column to Text in the import step.
- Before you send the file, open the CSV in Notepad. What you see there is what the recipient’s software will receive.
Mistakes that spoil a register, and the fix for each
Typing serials into a number column. This is how 0012345 becomes 12345 and a long battery serial ends in zeros. Fix: format as Text first, and check in Notepad.
Formatting after pasting. Microsoft says the Text format applies to numbers entered afterwards, and a custom format does not restore zeros already removed. Fix: clear the column and paste again into the Text-formatted cells.
Using only the accounting fields. A template built around cost, useful life and depreciation, like the finance minimums above, will not tell a facilities team which unit failed. Fix: keep the physical columns in the checklist.
Leaving as-installed data until after handover. Designing Buildings places manufacturer, model and warranty dates in the construction stage. Fix: record each unit while you are standing at it.
Not agreeing the columns with the client. The client defines the content, and Aconex advises issuing the headings to suppliers first. Fix: send the empty header row at the start of the job and ask for changes then.
Letting the register go stale. Designing Buildings stresses that it must be kept current once compiled. Fix: name one person who owns it after handover.
Filling the register from site with Baton
Baton is built to fill this register at the unit. Your crew opens a link or scans a QR code and types the six-digit job code. There is no account and no app to install, and it works with no signal. For each unit they photograph the nameplate and two views of the unit, then record its condition and location. Any equipment type can be named on site, so inverters, batteries, switchgear and heat pumps each get their own lines.
Two AI models read every nameplate. A person in your office checks manufacturer, model and serial against the photo before the handover can be made. The register is saved as a PDF, an Excel file and a CSV in your own Google Drive. Baton stores every data cell in the Excel file as text, so a serial like 0012345 stays as typed and 10-3 does not turn into a date.
The columns follow the checklist above: Item, Category, Manufacturer, Model, Serial number, Condition, Rating / capacity, Location, an optional Warranty column, Site tag when a job uses tags, Additional specifications, and a last column that points to the page in the PDF where that unit’s photographs sit. The Excel file also has a second sheet, Details by unit. Warranty dates are set once per equipment type.
What Baton does not do
The Excel and CSV files carry a pointer to the photos, not the pictures themselves. The PDF shows each nameplate and unit photograph on the unit’s own page. Baton does not hold test or commissioning results, issue certificates, file anything with a grid operator or scheme, or connect to your facilities software.
If the client wants a specific format such as COBie, or a CAFM import, treat Baton’s Excel as the clean source and map the columns yourself. Add test results and certificates through the attachments index, with a reference, a date and who issued each one.
Quick answers
- What should be in an asset register?
- At least a unique ID, category, manufacturer, model, serial number, location and condition, plus warranty end date and a reference to the evidence. Designing Buildings lists many more optional entries, such as supplier, installer, maintenance requirements and photographs.
- How do I create an asset register in Excel?
- Start with the headings, format the serial column as Text before typing, then add one row per unit copied from its nameplate. Agree the headings with the client first, and keep the register up to date after handover.
- What is an example of an asset register?
- One row per unit: item 003, battery, SampleCell, SC-100, serial 000123456789, new, battery store. The worked example above has six invented rows, and Yale’s nameplate data matrix shows a real client’s version.
- How do I stop Excel changing serial numbers?
- Format the column as Text before you type or paste. Microsoft says Excel otherwise drops leading zeros, shows long numbers in scientific notation and zeroes digits after the 15th. Check the CSV in Notepad before sending it.
- Does Baton give me an Excel equipment asset register?
- Yes. Baton makes one register per job as PDF, Excel and CSV from the nameplate photos your crew takes on site. Every data cell is stored as text, and each unit has a pointer to its photo page. Files are saved in your Google Drive.
- Who fills in the serial numbers in Baton?
- Two AI models read each nameplate, and a person in your office checks manufacturer, model and serial against the photo before the register can be generated. Baton shows the register only after that check.
Sources
- Designing Buildings: Asset register (typical entries, FM use, O&M manual)
- Designing Buildings: Creating an asset register for construction projects (who produces it and when)
- Scottish Government: Scottish Public Finance Manual, management of assets (minimum register fields)
- Yale Office of Facilities: Equipment nameplate data matrix overview (as-installed fields)
- Microsoft Support: Keeping leading zeros and large numbers
- Clean Energy Regulator: Inverter serial number ledger (text format, scientific notation, Notepad check)
- Aconex Help: Create an Asset Reference template for Handover (empty Excel template with column headers)